Gault - Maple- Patten 2017

Latest Update:

Maple, Gault, Patten, Lynn:

 

 

Week of October 16th:

Wearing course paving will be completed on this project starting Tuesday October 17th.  The contractor will be paving in the following order;

  1. Maple Drive

  2. Gault Road

  3. Lynn Drive

  4. Patten Road

  5. Maiden Lane

Note:  Any paving not completed on the 17th will be finished on Friday October 20th.

 

 

 

Expect extended delays, and possible detours during these operation.  Seek alternate routes.  Flaggers and operational signs will be deployed to assist motorist.

 

 

Older Updates:

 

Patten Road:

Is substantially complete.  Shoulder cleanup and loaming are in process, and will be ongoing through the week of August 27th.  Flaggers and operational signage shall be in place to assist motorists.  Expect minor delays.

 

John Goffe:

Week of August 28th:

Start Replacement of outdated and failing drainage pipes.  Expect daytime delays and detours during this operation.  Flaggers and operational signage shall be in place to assist motorists. 

 

Week of September 3rd:

Complete installation of new drainage pipes, and install new headwalls.  Patch trenches and crack seal the remainder of the road.  Expect delays and detours during this operation.

 

 

Gault Road:

Week of July 30th:

Cleanup of shoulders, loaming, and seeding work is ongoing and scheduled for completion on August 4th.  Roadway subject to alternating lane closures; expect minor delays.  Flaggers and operational controls will be in place during this period.

 

 

Patten Road:

Note: Patten Road will continue to be closed to through traffic for the next few weeks and is scheduled to reopen the week of August 7th.

 

Week of July 30th:

Closed drainage system is completed. The contractor is scheduled to excavate roadway material  in preparation of underdrain construction.

 

Week of August 6th:

Complete underdrain system, and install gravel base, pave binder.

 

John Goffe:

Removal and replacement of existing plastic and metal road crossing pipes is tentatively scheduled the week of August 6th.

Gault Road: Week of July 16th: Gault Road is nearing substantial completion, binder pavement driveway tie-ins are complete. Fine grading and cleanup of shoulders, loaming, and seeding will be complete by the end of July. The Roadway will be subject to alternating lane closures; expect minor delays.

 

Patten Road: Patten Road will continue to be closed to through traffic for until mid-August. Operational controls and flaggers will assist motorist around the closure. Week of July 16th Installation of the closed drainage work will commence on Patten Road.

 

Week of July 23rd Complete closed drainage system on Patten Road.

Gault Road:

Week of July 2nd:

Road closures are scheduled from the intersection of John Goffe to the roundabout on Meetinghouse Road M-F 6:30AM-4:30PM.  The Contractor will be placing select gravel materials during this period.  Once complete, fine grading and paving operations will commence and are tentatively scheduled at the end of the week for the entire Gault Road reconstruction area. Operational signs will be in place to assist with traffic control.

 

Week of July 9th:

Cleanup, loaming and seeding operations are scheduled.

Patten Road Construction Project- Phase III

 

Phase II of the Gault/Maple/Patten Roads Project is substantially complete and Gault Road is open to through traffic. Starting July 12, 2017 Contractor will begin reconstruction work on Patten Road between #25 and #69.  During construction Patten Road will be closed to all through traffic, access to this area will be via the Meetinghouse Road Roundabout.  A barrier will be placed across Patten Road just north of #63 Patten Road. Operational controls will assist motorist along County Road to Gault Road to Meetinghouse Road detour. 

Reconstruction of Patten Road is expected to substantially complete by mid-August.

 

Gault Road:

Week of June 18th:

Finish removing asphalt, and rough subgrade.  Begin installing underdrain.

 

Week of June 25th:

Continue installing underdrain on both sides of Gault Road.  Begin installing gravel base.

 

Patten Road:

Week of June 18th:

Continue tree clearing operations.

 

Week of June 25th:

Continue tree clearing operations.

 

Phase II Construction

 

Beginning the week of May 22, 2017, the contractor is scheduled to begin Phase II construction on Gault Road between Dunnington Way and John Goffe Drive.  This phase is scheduled for substantial completion the week of July 17, 2017.  Gault Road will be closed to all through vehicles between Liberty Hill Road and John Goffe Drive.  Implementation of operational controls will assist motorists around the work zone from Meetinghouse Road to Liberty Hill Road.  A barricade will be placed on Gault Road between 62 & 65 Gault Road. 

 

On nights and weekends, access to Gault Road east of 62 Gault Road, John Goffe Drive, Maple Drive, and Mayflower Drive will be via the roundabout on the east end of the project.  Access to the properties west of 65 Gault Road will be via Liberty Hill Road. 

Gault Road, Maple Drive and Patten Road are scheduled for reconstruction in 2017. 

Gault, Maple, Patten Project; Phase I

Gault Road:

4/24 – Tree clearing and canopy trimming.  Expect minor delays.

5/1-5/5 - Tree clearing and canopy trimming.  Expect minor delays.

 

Maple Drive:

Drilling and Blasting:

4/24-4/25 – Drilling and blasting operations will be occurring between #52 and #47 Maple Drive.

4/25-4/28 – Drilling and blasting operations will be occurring between #6 and #10 Maple Drive.

Under Drain:

4/24-4/28 – Installation of the underdrain system will begin on Monday 3/24 and continue through Friday 3/28.  The area of work will be located between #2 Maple Drive and # 30 Maple Drive.

Excavation:

5/1 – 5/3 – Complete the excavation of the road box, and install the road base from Gault Road to #30 Maple Drive.

5/3-5/5 – Asphalt Removal and road box excavation from #30 Maple Drive to # 40 Maple Drive.

 

Patten Road:

May – Tree clearing and canopy trimming.  More specific update to come.

Road work to start in June or July.

Phase I Construction

On Monday March 27, 2017 Phase I of the Gault, Maple, and Patten Road Project will begin.  Phase I work will include improvements to the closed drainage system and road reconstruction work on Maple Drive, Phase I is scheduled to be substantially complete on or about May 15, 2017.  Work will begin at the intersection of Maple Drive and Gault Road nearest Mayflower Lane.  In conjunction with the work on Maple Drive, there will also be tree trimming and clearing along Gault Road and Maple Drive.

Click HERE to view plans for Gault Road

Get Updates On Bedford's Road Improvement Projects