Old Bedford/Holbrook Rd.


The project is substantially complete.
 

5/23 — 6/3

  • Continue Misc Cleanup

  • Start Top Paving on Side Roads off of Old Bedford/Holbrook Monday 5/23 weather permitting. Side roads include:

    Beards Hill Rd.
    Grandview Dr.​
    Hickory Ln.
    Timberlane Rd.
    Roblin Rd.
    Curtis Ave.
    Old Bedford Rd.

 

Old Bedford Rd., Old Bedford Way, Garrison Dr., Galloway Rd. are set to be complete by late June. 

 

Please reload

Construction schedule for 2016