Our Past Completed  Projects:

New watermains have been installed on Preysnar Road, Tirrell Road, Back River Road, Smith Road and Green Meadow Lane. Construction crews continue to install service connections from the main to the street on Green Meadow Lane.

Information from the NHDES

IMG_1295.JPG

Cider Mill Road has been re-opened to through traffic.  The Cider Mill Road Bridge over McQuade Brook has been reconstructed and the project is substantially complete.    Click HERE to view plans

This project included the realignment of Campbell Road & North Amherst Road intersection.  The most notable changes was the reconfiguration of the triangular island and realignment of Campbell Road 24 feet easterly at North Amherst Road.This proposal has significantly increased intersection sight distance for vehicles on Campbell Road looking east.

 

Click HERE to view plans for North Amherst and Campbell Road.

North Amherst/Campbell Road 

Donald Street

Donald St. and associated Side Streets Natural Gas Extension Project:

Gault, Maple, Patten Phase III 

 

Maple, Gault, Patten, Lynn:

Wearing course paving is now completed on this project.

 

 

This project consists of the resurfacing of Gage Road, Pheasant Run Road and the southernmost portion of Barrington Drive.  

 

This project is substantially complete.

Click HERE to view plans

20190419_073219.jpg

Little League Parking Area

The parking lot reconstruction plans are complete, with some modifications to the gravel drainage swale separating the two lots, about 108 parking spaces can fit on the Little League side of the lot which is an increase of 10 spaces over the concept proposal in December but still 12 less than the 120 "unofficial" spaces there today.

See the plan here

 

Project and utility relocations are complete as of June 1, 2017 - with new pavement and, curbing .

 

Lindahl Road

Click HERE for full project design

 

The project is substantially completed with shoulder gravel and clean up scheduled for completion by the end of September 2017. 

Click HERE to see the project under construction.

Click HERE for more information on this project.

Wallace Rd. (South)

IMG_0466
IMG_3458
IMG_3462
IMG_3467
IMG_0478
IMG_0474
IMG_0470

Joppa Hill Rd.

The Joppa Hill project was a rehabilitation project budgeted at $650,000 which stretched from New Boston Road to the Goffstown town line. This project's focus was to improve drainage, implement erosion control measures, add pavement rehabilitations, and mitigate environmental concerns at the head waters of McQuaid Brook. 

 

OBJECTIVES

 

Drainage and erosion improvements

Road widening

Site distance improvements at:

-  Polly Peabody Road

-  Parker Lane

-  Weber Lane

Paving

 

Click below for full project design

Phase 1               Phase 2

IMG_1409.JPG
IMG_1809.JPG
IMG_1416.JPG
IMG_1411.JPG
IMG_1812.JPG

The Pines

 Click HERE for full project design

This project enhanced residential streets and utility infrastructure. The limits of the project included portions of Whittemore St. and Wayside Dr., as well as Plumber Rd. and Seabee St. in their entirety.

 

OBJECTIVES

 

Reclaim and pave roads

Extension of utility of infrastructure by Liberty Utilities

Proposed natural gas utility extensions.

Seabee St. gas extension information can be found HERE

 

 

utilities.jpg
Wallace Road (Middle)

Click HERE for full project design

The 2016 focus was to complete roadway construction between North Amherst Road and Benedictine Park and also a segment between Whisky Rebellion and Ministerial Road. Final paving and striping were completed in July.

IMG_4997
IMG_5001
IMG_4993
IMG_2753
IMG_5011
IMG_5003
IMG_5005
IMG_5010
IMG_5002
IMG_5012
IMG_2167
Old Bedford / Holbrook Road

Click HERE for full project design

This project was completed in August 2016.

Meadow Road

 

This project is complete. A drainage culvert failed resulting in a closure of Meadow Road. 

Click HERE to view plans
Nashua Road

Construction of sidewalks near the high school is complete. The town is currently seeking dynamic signage to complement the intersection in front of the high school.

Pulpit Road from New Boston Road to Mountain Road, Three Corners Road, Rockbound Road, Mountain Road and Pond Point Drive.  Within the Three Corners neighborhood, the streets will be milled and all catchbasins shall be reset to the proper grades, followed repaving.

 

Project is complete.  

 

Thank you for your patience while we work to improve the roadways.

Click here to view plans for Pulpit Road

Pulpit Road Neighborhood

Work complete 2020 on the I-293/Route 101 Bridge over the Merrimack River.  

IMG_0113.jpg

Liberty Hill Road

Roadway Reconstruction

This project consisted of the reconstruction of Liberty Hill Road from Meadow Road to County Road. Work included the replacement of culverts, installation of underdrain and rebuilding of the roadway.   2020

Click HERE to view plans for Liberty Hill Road.

NHDOT:

Route 101 Improvements

NHDOT Route 101 Improvements work on Route 101 addressed roadway reconstruction and additional drainage installations between Shaw Drive and Route 114.

If you have any questions or need any additional information regarding the proposed project, call (603) 271-2171.  Other information about the project can be found on the NHDOT web site

Eversource Line Cutting/Tree Clearing

Eversource and their subcontractor, Asplundh,  cleared the lines/trimming trees, starting in the southwest corner of Bedford. 2020

IMG_1863.JPG

Donald Street and Surrounding Roads Roadway Reconstruction

Roadway Improvements were be made to Donald Street, from Old Bedford Road to the town Line, Savoie Street, Swan Avenue, Hall Street, Johnson Street, Darling Street, Merry Street, Woodlawn Avenue, Lawes Avenue, Dery Street and Gendron Street. The project included culvert replacement, drainage improvements, underdrain installation and new pavement. It also included resurfacing of Cote Lane, Sandstone Drive and Old Bedford Road from Donald Street to the Route 114 bridge.

Complete 2020

 

Click here to view plans.

The Town of Bedford is working to improve several key areas of its integral roadways.    

© 2020 by the Town of Bedford, New Hampshire

55 Constitution Drive, 2nd Floor

Bedford, NH   03110

(603) 472-3070

Bedford Cares:

Please call 603-792-1319 if you are in need of non-emergency assistance or are looking to volunteer in any way.

 

https://www.facebook.com/BedfordNHCares/

  • Twitter