Gault, Maple, Patten Project; Phase I

March 22, 2017

 

 

Phase I Construction

 

On Monday March 22, 2017 Phase I of the Gault, Maple, and Patten Road Project will begin.  Phase I work will include improvements to the closed drainage system and road reconstruction work on Maple Drive, Phase I is scheduled to be substantially complete on or about May 15, 2017.  Work will begin at the intersection of Maple Drive and Gault Road nearest Mayflower Lane.  In conjunction with the work on Maple Drive, there will also be tree trimming and clearing along Gault Road and Maple Drive.