Wallace Road South Project

June 16, 2017

 

Beginning the week of June 19, 2017, Continental Paving will begin paving operations on seven roads abutting Wallace Road.  Work will begin on Stage Coach Lane and Wiggin Road in preparation for main line work on Wallace Road scheduled to occur over the following two weeks. Work will consist of Asphalt trimming, patching, and binder paving.

 

Starting week of June 24th  the Contractor is scheduled to pave the wearing course of asphalt on the following roads: Wiggin Road, Rutledge Road, Stage Coach Lane, Benning Way, Elder Williams Road, Alder Way, County Road West, and Wallace Road from Merrimack Town Line north to NH Route 101.  This work will progress as weather permits. Seek alternate routes or expect significant delays.

 

Upon completion of the roadway paving operations, the Contractor will pave driveway aprons, place shoulder gravel and complete punch list items.  

 

 

 

Share on Facebook
Share on Twitter
Please reload

Follow Us