Gault, Maple, Patten Phase II

June 30, 2017

 

 

Gault Road:

Week of July 2nd:

Road closures are scheduled from the intersection of John Goffe to the roundabout on Meetinghouse Road M-F 6:30AM-4:30PM.  The Contractor will be placing select gravel materials during this period.  Once complete, fine grading and paving operations will commence and are tentatively scheduled at the end of the week for the entire Gault Road reconstruction area. Operational signs will be in place to assist with traffic control.

 

Week of July 9th:

Cleanup, loaming and seeding operations are scheduled.

 

 

 