Gault, Maple, Patten Update

August 1, 2017

 

 

 

Gault Road:

Week of July 30th:

Cleanup of shoulders, loaming, and seeding work is ongoing and scheduled for completion on August 4th.  Roadway subject to alternating lane closures; expect minor delays.  Flaggers and operational controls will be in place during this period.

 

 

Patten Road:

Note: Patten Road will continue to be closed to through traffic for the next few weeks and is scheduled to reopen the week of August 7th.

 

Week of July 30th:

Closed drainage system is completed. The contractor is scheduled to excavate roadway material  in preparation of underdrain construction.

 

Week of August 6th:

Complete underdrain system, and install gravel base, pave binder.

 

John Goffe:

Removal and replacement of existing plastic and metal road crossing pipes is tentatively scheduled the week of August 6th.

 