Wallace Road South Update


The wearing course of asphalt is scheduled for the entire Wallace Road South segment on Wednesday 07/12/2017 6AM-5PM. Paving will begin in the SB lane at the north end of the project near NH Route 101 and progress southerly to the Merrimack Line. The contractor will then pave the NB lane beginning at the northerly end of the project near NH Route 101 and progress southerly to the Merrimack town line. Seek alternative routes or expect significant delays.

#WallaceRoadSouth

13 views0 comments

The Town of Bedford is working to improve several key areas of its integral roadways.    