Gault, Maple, Patten Update

Jeff Foote

Gault, Maple, Patten Project Phase III: Gault Road: Week of July 16th: Gault Road is nearing substantial completion, binder pavement driveway tie-ins are complete. Fine grading and cleanup of shoulders, loaming, and seeding will be complete by the end of July. The Roadway will be subject to alternating lane closures; expect minor delays. Patten Road: Patten Road will continue to be closed to through traffic for until mid-August. Operational controls and flaggers will assist motorist around the closure. Week of July 16th Installation of the closed drainage work will commence on Patten Road. Week of July 23rd Complete closed drainage system on Patten Road.