WBCC work schedule for the month of October

  • Jeff Foote
  • Oct 5, 2017
  • 1 min read

The week of October 9, 2017 will include the paving of First Street, Second Street, and Third Street, and the reclaiming and paving of Hill Top Drive, Wilkins Street, and Plymouth Street Extension. Driveway aprons, raising of drainage structures, and loam and seeding is schedule for the week of October 16, 2017. Wearing course pavement, and job clean-up is scheduled for the week October 23, 2017.