Greenfield Parkway Bridge Project

Bridge is NOW OPEN.

Th bridge failed on Friday 1/26/2024. Preliminary investigations are complete and repair plans are being prepared.

 

 

 

State Aid Bridge (SAB) Project Design Schedule

*the following dates are our best estimates and are subject to change*

Project Name: Bedford                   

Project Number: 21684

Project Description: Greenfield Parkway over Riddle Brook, Bridge No. 157/068, SAB Project: Bridge Replacement

Funding Source: SAB

Project Manager: Brian Desfosses, PE

Target Dates (Subject to change)

  • Start Engineering Study - 4/26/2024

  • Approve Engineering Study - 9/3/2024

  • Approve Preliminary Design - 9/27/2024

  • Begin Final Design and Right-of-Way (ROW) Acquisition Process - 10/11/2024

  • Complete National Environmental Policy Act (NEPA) Process - 10/30/2024

  • Receive Notice to Proceed to Advertise Project from NHDOT - 12/11/2024

  • Advertising Date - 12/11/2024

  • March Ballot for bid award - March 2025

  • Construction Completion - December 2025

Plans: Greenfield Bridge Plans

Schedule: Greenfield Bridge Proposed Timeline

Bid Ad: Greenfield Ad Page

Contract Specs: Proposal

Click HERE to view the latest DPW report related to this project.

Click HERE to view the final Geotechnical Engineering Report.

Task
Total Hours
Finalize ROW & Easements
0
Utility Coordination
16
Develop Cost Estimate
35
Prepare Contract Proposal & Specifications
74
Project Meetings (Assume 1)
4
Bid Phase Services
Bid Assistance
- Develop Construction Bid Advertisement
2
- Prepare Bid Addenda as Necessary
16
- Conduct a Pre-Bid Meeting
9
- Attend Bid Opening
3
- Review and Summarize Bids; Prepare Recommendation Letter
38

Photo Gallery

GreenfieldCrane

Crane

GreenfieldPileDriving

Pile Driving

GreenfieldCofferdam

Cofferdam

IMG_4543
Greenfield Parkway Bridge 1_edited

Bridge Closure

Greenfield Parkway Bridge 2

Collapsed Pavement

Greenfield Parkway Bridge 3

Further Collapsing of Pavement

Greenfield Parkway Bridge 5

Drone Shot of Detached Metal Arch

Greenfield Parkway Bridge 4

View of Detached Metal Arch

Greenfield Parkway Bridge 6

Close Up Drone Shot of Collapsed Metal Arch

The Town of Bedford is working to improve several key areas of its integral roadways.    

© 2026 by the Town of Bedford, New Hampshire

55 Constitution Drive, 2nd Floor

Bedford, NH   03110

(603) 472-3070

Bedford Accreditation Logo.png
bottom of page