Veronica Dr, Horizon Dr & Smith Rd

Project Status: Complete

Project Notes: 
Veronica Dr - Tree removal and trimming, reclaimed the entire road (recycle the existing asphalt into the road base), completed fine grading, a full 4” repaving effort (2.5” binder, 1.5” wearing still to be installed this fall), lawn restoration work, and the installation of compacted shoulder gravel.  Project completed fall 2024.
Horizon Dr - Installed drainage ditches near the intersection of Veronica Drive, some tree removal and trimming, installed pavement shim to reestablish road profile, and then perform a 1.5” overlay in the same area, lawn restoration work.   Project completion is anticipated in early fall 2024.
Smith Rd - Performed camera inspection of the existing drainage system, and replaced/240 lf of pipe, and installed a direct Inlet structure to address a wet area in the same area, to prevent an icing issue.  Tree removal and trimming, remove several damaged areas of pavement and repave (2” spot inlays).  Finally, a full pavement overlay, and compacted shoulder gravel was installed this fall.

DJI_20240903122842_0215_D.JPG
bottom of page