Gault, Maple, Patten, Lynn Update
Maple, Gault, Patten, Lynn: Week of October 16th: Wearing course paving will be completed on this project starting Tuesday October 17th. ...
Oct 16, 20171 min read


Gault, Maple, Patten Phase III and North Amherst and Campbell Update
Patten Road: Is substantially complete. Shoulder cleanup and loaming are in process, and will be ongoing through the week of August 27th....
Aug 26, 20171 min read