Gault, Maple, Patten Phase III and North Amherst and Campbell Update


Patten Road:

Is substantially complete. Shoulder cleanup and loaming are in process, and will be ongoing through the week of August 27th. Flaggers and operational signage shall be in place to assist motorists. Expect minor delays.

John Goffe:

Week of August 28th:

Start Replacement of outdated and failing drainage pipes. Expect daytime delays and detours during this operation. Flaggers and operational signage shall be in place to assist motorists.

Week of September 3ird:

Complete installation of new drainage pipes, and install new headwalls. Patch trenches and crack seal the remainder of the road. Expect delays and detours during this operation.

North Amherst Campbell Road:

Week of September 3ird:

Construction on this project will be started during this week. The contractor will be concentrating their efforts on the new re-alignment of the intersection of North Amherst and Campbell Road. During this time expect daytime delays and possible detours through this area. Flaggers and operational signage will be in place to assist motorist.

Week of September 10th:

Construction at the intersection of North Amherst and Campbell Road will be continuing during this week. Expect daytime delays and possible detours during this work.