North Amherst and Campbell Roads Project Update


Week of September 17th: M-F 7AM-5PM

The contractor will continue to concentrate their efforts on phase I of the project which includes the roadway from North Amherst Road/Campbell Road intersection the Steeple View Lane/Wellesley Drive intersection. The contractor is scheduled to complete the closed drainage system, and prepping for reclaiming operations. Expect alternating lane closures, delays and detours through this area. Flaggers and operational signage will be in place to assist motorist.

Week of September 24th: M-F 7AM-5PM

During this week he contractor will be paving and completing cleanup in Phase I, and starting the closed drainage repairs in Phase II of the project. Phase II will consist of the area from the intersection of North Amherst and Campbell Road east to the intersection of Wallace Road and North Amherst. Expect alternating lane closures, delays and detours through this area. Flaggers and operational signage will be in place to assist motorist.

Note: Schedule is subject to change.

46 views0 comments

Recent Posts

See All

TRANSFER STATION IMPROVEMENTS

Phase I improvements are scheduled to commence on August 12th , work includes access road realignment, scale house relocation and expanded trailer staging area. This project is expected to be substant

bottom of page